60 kW Solar PV + Battery Storage Load-Side Interconnection for Fire Station

النوع مخطط أحادي الخطالمعيار IEEE Std 315 + ANSI device numberingالمحرّك schematex-sldآخر تحديث 6‏/10‏/2026
60 kW Solar PV + Battery Storage Load-Side Interconnection for Fire Station
Drawing preview
السيناريو

A fire station with 480/277V utility service adds a 60 kW solar PV array and 50 kW/100 kWh battery storage under a load-side interconnection. The SLD shows the main service disconnect, PV/battery breakers, a 480V main panel, and a 208/120V subpanel serving critical and normal loads.

ما الذي يتضمنه هذا الرسم

اقرأ القرارات الكامنة وراءه.

01

Load-side interconnection at 400A main distribution panel with 100A PV and battery breakers

02

Dedicated watthour_meter for PV production monitoring

03

Delta-wye transformer to derive 208/120V for lighting, receptacles, and fire alarm loads

04

Battery modeled as UPS source for simplicity

For commercial or municipal facilities (fire stations, schools, small offices) evaluating NEC 705.12 load-side interconnections of solar PV plus battery storage where a 480V service feeds 208/120V load panels.