SUBSTATION

33 kV to 11 kV primary substation single line diagram

This substation single line diagram shows a 33 kV to 11 kV primary distribution substation. The grid incomer passes through a line disconnector, metering and protection CT, and a 1250 A vacuum circuit breaker to the 33 kV bus. A 20 MVA power transformer feeds an 11 kV bus through a second vacuum breaker.

UPDATED 2026-09-23
TYPESld
USE-CASESubstation
EXAMPLE33 kV to 11 kV primary substation single line diagram
Make this diagram your own.

Open it in the AI editor with a prompt pre-filled — keep what works, change what doesn't.

CASE ANALYSIS

Scenario

This primary substation steps a 33 kV grid supply down to an 11 kV feeder bus for industrial, urban, and rural distribution circuits.

Key decisions

  • HV switching: A line disconnector, CT, and 33 kV VCB control the incoming supply.
  • Power transformation: A 20 MVA transformer establishes the 33/11 kV interface.
  • Differential protection: The 87T relay identifies transformer internal faults.
  • Feeder separation: Three 630 A VCBs protect distinct 11 kV distribution circuits.

When to reuse this

Use this for a conceptual primary substation layout. Real substation design needs detailed CT ratios, protection zones, earthing, and utility standards.

FAQ

Frequently asked questions

What does 87T mean?01
It is the ANSI function number commonly used for transformer differential protection.
Why are VCBs shown at both transformer sides?02
They allow protection and isolation on the HV and MV connections of the transformer.
Is a CT only for metering?03
No. Current transformers can supply both metering and protection relays, often through separate cores.