An underground gold mine requires reliable 440V power distribution from a 11kV grid supply, with automatic transfer to a 500 kW diesel generator for critical loads during utility outages.
Cosa contiene questo disegno
Leggi le decisioni che ne stanno alla base.
01
11kV grid supply stepped down to 440V via 1 MVA transformer
02
500 kW generator integrated via ATS for critical bus
03
Critical loads (ventilation, pumping, lighting) connected to generator-backed bus
04
Non-critical load (conveyor) fed directly from main bus
Underground mining operations requiring continuous power for safety-critical systems, applicable to gold, copper, or coal mines with similar electrical infrastructure.