상황
A residential UK property with a 10kW PV system requiring G99 grid connection, including a backup power solution for essential appliances and export limitation to meet distribution network operator requirements.
이 도면에 담긴 내용
그 이면의 의사결정을 읽어 보세요.
01
Use of a transfer switch to island critical loads during grid outage
02
Export limitation relay set to 3.68 kW to comply with G98-level export constraints
03
Generation metering at the point of common coupling
When designing a single-line diagram for a UK solar installation over 16A per phase, with backup capability and export limitation requirements.