This activity-on-arrow diagram shows how a library can coordinate a single-room renovation. A survey and plan approval come first, then shelf ordering, room clearing and light wiring proceed in parallel. The reopening event depends on all three activities, making the required readiness condition clear. The arrows hold the work and durations, while the nodes mark the points where project conditions are met. It is useful for facilities teams that need to explain a compact renovation sequence to library staff, vendors and contractors. Adapt the tasks for permits, flooring, equipment delivery or a staged reopening when the project needs them.

類型 PERT/甘特圖標準 PMI PMBOK 7 + Moder 1983 (AON/PDM)引擎 schematex-pert更新時間 2026/9/24
Library renovation (AOA)
Drawing preview
需求

“Create an activity-on-arrow diagram for a library renovation: survey the room, approve the plan, order shelves, clear the room, wire lights, then reopen the library.”

接著試試Add a fire inspection before reopening.Change shelf ordering to take fifteen days.
這張圖裡有什麼

看懂背後的決策。

01Plan approval

Ordering and site work start after the plan is approved.

02Parallel preparation

Shelves, clearing and lighting can proceed together.

03Reopening event

All preparation activities must finish before reopening.

Use this for a renovation with an approval gate and several required workstreams.

瀏覽所有 PERT/甘特圖 範本 →

常見問題

常見問題

What work can overlap?

Shelf ordering, clearing and lighting all follow plan approval and can overlap.

Why is reopening an event?

It happens only after every incoming renovation activity is complete.

Can an inspection be added?

Yes, add it before reopening and make the reopening activity depend on it.