“Create an activity-on-arrow diagram for a library renovation: survey the room, approve the plan, order shelves, clear the room, wire lights, then reopen the library.”
看懂背後的決策。
Ordering and site work start after the plan is approved.
Shelves, clearing and lighting can proceed together.
All preparation activities must finish before reopening.
Use this for a renovation with an approval gate and several required workstreams.
常見問題
What work can overlap?
Shelf ordering, clearing and lighting all follow plan approval and can overlap.
Why is reopening an event?
It happens only after every incoming renovation activity is complete.
Can an inspection be added?
Yes, add it before reopening and make the reopening activity depend on it.