Construction project Gantt timeline

A construction project Gantt timeline turns a building sequence into a visible dependency plan. It begins with site preparation, foundation and framing, then separates the trade work that must be complete before drywall and finishes. The final inspection is placed after the necessary completion work. This makes it easier to discuss what can proceed in parallel and which delay would affect handover. It is a planning view, not a substitute for a detailed construction schedule or permit plan.

類型 PERT/甘特圖標準 PMI PMBOK 7 + Moder 1983 (AON/PDM)引擎 schematex-pert更新時間 2026/9/24
Construction project schedule
Drawing preview
需求

“Create a construction project timeline with site preparation, foundation, framing, roofing, electrical and plumbing rough-in, drywall, painting, finish work, and final inspection.”

接著試試Add permit approval before site preparation.Change roofing to 12 days.
這張圖裡有什麼

看懂背後的決策。

01Sequence structural work

Foundation and framing precede trade work.

02Coordinate trades

Electrical and plumbing rough-in both precede drywall.

03Protect the finish date

Inspection follows all finish work.

Use for an early work-sequence discussion; confirm site, contract and permit constraints separately.

瀏覽所有 PERT/甘特圖 範本 →

常見問題

常見問題

Why are electrical and plumbing separate tasks?

They are distinct trade activities that can often proceed in parallel after framing.

What follows rough-in work?

Drywall commonly follows the relevant rough-in work, then painting and finish work.

Is this a construction drawing?

No. It is a project schedule for task order and duration.