“Create a product launch timeline with market research, design mockups, backend API, frontend build, QA testing, marketing collateral, and a launch event with their dependencies.”
看懂背後的決策。
Design and development follow the market input.
Backend and design can overlap after research.
The launch needs both tested product and marketing material.
Use for a small launch plan where task order is more important than calendar detail.
常見問題
What does this schedule show?
It shows the tasks needed for launch, their durations and the work that must happen before each task.
Can tasks run in parallel?
Yes. Tasks with different predecessors can proceed at the same time.
Why use dependencies?
Dependencies show which work would delay a later milestone if it slips.