Film production critical path

This critical path diagram captures the main dependencies of a short film production. A locked script enables both casting and location work. Shooting cannot begin until those two preparation paths are complete, and editing then leads directly to master delivery. The diagram is intentionally compact so a producer can discuss the work that controls the delivery date without losing the key parallel preparation. Add permits, rehearsal, sound, color and distribution tasks when they are meaningful project constraints.

النوع PERT / Ganttالمعيار PMI PMBOK 7 + Moder 1983 (AON/PDM)المحرّك schematex-pertآخر تحديث 24‏/9‏/2026
Film production critical path
Drawing preview
الطلب

“Create a critical path diagram for film production: lock the script, cast roles, find locations, shoot scenes, edit the picture, then deliver the master.”

جرّب إذنAdd sound mixing before delivery.Change shooting to take ten days.
ما الذي يتضمنه هذا الرسم

اقرأ القرارات الكامنة وراءه.

01Script gate

Casting and location work follow a locked script.

02Shoot gate

Both cast and locations must be ready.

03Delivery chain

Editing follows the shoot.

Use for a small production schedule.

تصفّح جميع قوالب PERT / Gantt ←

الأسئلة الشائعة

أسئلة شائعة

What can happen in parallel?

Casting and location work can proceed after script lock.

What controls editing?

Editing starts after shooting.

Can sound be added?

Yes, make delivery depend on it.