PROJECT PLANNING

Film production critical path

This critical path diagram captures the main dependencies of a short film production. A locked script enables both casting and location work. Shooting cannot begin until those two preparation paths are complete, and editing then leads directly to master delivery. The diagram is intentionally compact so a producer can discuss the work that controls the delivery date without losing the key parallel preparation. Add permits, rehearsal, sound, color and distribution tasks when they are meaningful project constraints.

UPDATED 2026-09-24
TYPEPert
EXAMPLEFilm production critical path
Make this diagram your own.

Open it in the AI editor with a prompt pre-filled — keep what works, change what doesn't.

CASE ANALYSIS

Scenario

A production combines casting and location work before shooting.

Key decisions

  • Script gate: Casting and location work follow a locked script.
  • Shoot gate: Both cast and locations must be ready.
  • Delivery chain: Editing follows the shoot.

When to reuse this

Use for a small production schedule.

FAQ

Frequently asked questions

What can happen in parallel?01
Casting and location work can proceed after script lock.
What controls editing?02
Editing starts after shooting.
Can sound be added?03
Yes, make delivery depend on it.