Film production critical path

This critical path diagram captures the main dependencies of a short film production. A locked script enables both casting and location work. Shooting cannot begin until those two preparation paths are complete, and editing then leads directly to master delivery. The diagram is intentionally compact so a producer can discuss the work that controls the delivery date without losing the key parallel preparation. Add permits, rehearsal, sound, color and distribution tasks when they are meaningful project constraints.

類型 PERT/甘特圖標準 PMI PMBOK 7 + Moder 1983 (AON/PDM)引擎 schematex-pert更新時間 2026/9/24
Film production critical path
Drawing preview
需求

“Create a critical path diagram for film production: lock the script, cast roles, find locations, shoot scenes, edit the picture, then deliver the master.”

接著試試Add sound mixing before delivery.Change shooting to take ten days.
這張圖裡有什麼

看懂背後的決策。

01Script gate

Casting and location work follow a locked script.

02Shoot gate

Both cast and locations must be ready.

03Delivery chain

Editing follows the shoot.

Use for a small production schedule.

瀏覽所有 PERT/甘特圖 範本 →

常見問題

常見問題

What can happen in parallel?

Casting and location work can proceed after script lock.

What controls editing?

Editing starts after shooting.

Can sound be added?

Yes, make delivery depend on it.