“Create an activity-on-arrow diagram for a clinic renovation: survey rooms, approve the layout, order fixtures, clear rooms, install wiring, then reopen the clinic.”
Die dahinterstehenden Entscheidungen verstehen.
Do not order or clear rooms until the layout is approved.
Fixture ordering, room clearing and wiring can proceed together.
Reopening waits for all three preparation activities.
Use this pattern when several activities begin after one approval and converge on a single handover event.
Häufige Fragen
Why are three activities parallel?
They all start after layout approval and can progress independently.
What delays reopening?
A delay to fixtures, clearing or wiring delays the reopening event.
What do the nodes mean?
They mark project events at the start or finish of activities.