Clinic renovation activity-on-arrow diagram
This activity-on-arrow diagram plans a small clinic renovation from the initial survey to reopening. The survey leads to layout approval, which releases three streams of work: ordering fixtures, clearing rooms and installing wiring. Each arrow is an activity with a duration, while the joining event before reopening shows that all three streams must be complete. It is a concise way to discuss the handover point with facilities staff, contractors and clinic managers. Change the activities and durations to match the rooms, equipment and approval process in your own project.
Open it in the AI editor with a prompt pre-filled — keep what works, change what doesn't.
Scenario
A small clinic must coordinate renovation work before reopening.
Key decisions
- Approval gate: Do not order or clear rooms until the layout is approved.
- Parallel work: Fixture ordering, room clearing and wiring can proceed together.
- Reopening event: Reopening waits for all three preparation activities.
When to reuse this
Use this pattern when several activities begin after one approval and converge on a single handover event.
Frequently asked questions
Why are three activities parallel?
What delays reopening?
What do the nodes mean?