Hospital wing fit-out critical path
This critical path diagram plans a hospital-wing fit-out around the dependencies that affect commissioning. Layout approval starts partition work and equipment ordering. Medical gas follows partitions, and equipment installation cannot begin until both the equipment has arrived and the gas infrastructure is ready. Commissioning then verifies the completed wing. The network is a compact planning aid for facilities teams, clinical engineering and contractors. Add infection-control checks, electrical work, permits and staff readiness where they are genuine constraints on opening the area.
Open it in the AI editor with a prompt pre-filled — keep what works, change what doesn't.
Scenario
A hospital fit-out combines building work and equipment delivery.
Key decisions
- Layout gate: Partitions and equipment ordering follow approval.
- Installation gate: Equipment waits for delivery and medical gas.
- Commissioning gate: The wing is commissioned after installation.
When to reuse this
Use for a small clinical fit-out.
Frequently asked questions
Why does equipment wait?
What is commissioning?
Can equipment be ordered early?
More project planning examples
Try the diagram makers.
Tweak it with chat, export PNG/SVG, or fork it for your own use case.