ChatDiagram
project planning · healthcare

Hospital wing fit-out critical path

This critical path diagram plans a hospital-wing fit-out around the dependencies that affect commissioning. Layout approval starts partition work and equipment ordering. Medical gas follows partitions, and equipment installation cannot begin until both the equipment has arrived and the gas infrastructure is ready. Commissioning then verifies the completed wing. The network is a compact planning aid for facilities teams, clinical engineering and contractors. Add infection-control checks, electrical work, permits and staff readiness where they are genuine constraints on opening the area.

Type PERT / CPM network & Gantt chartStandard PMI PMBOK 7 + Moder 1983 (AON/PDM)Engine schematex-pertUpdated 9/24/2026
Hospital fit-out critical path
Drawing preview
The request

“Create a critical path diagram for a hospital wing fit-out: approve layout, install partitions, order equipment, run medical gas, install equipment, then commission the wing.”

Then tryAdd a safety inspection before commissioning.Change equipment ordering to take nine days.
What is in this drawing

Read the decisions behind it.

01Layout gate

Partitions and equipment ordering follow approval.

02Installation gate

Equipment waits for delivery and medical gas.

03Commissioning gate

The wing is commissioned after installation.

Use for a small clinical fit-out.

More like this

Other examples in this family.

Browse all pert / gantt templates →

FAQ

Common questions

Why does equipment wait?

It needs delivery and medical-gas readiness.

What is commissioning?

It verifies the wing is ready for use.

Can equipment be ordered early?

Yes, after layout approval.