“Create a critical path diagram for a hospital wing fit-out: approve layout, install partitions, order equipment, run medical gas, install equipment, then commission the wing.”
Comprenez les décisions qui le sous-tendent.
Partitions and equipment ordering follow approval.
Equipment waits for delivery and medical gas.
The wing is commissioned after installation.
Use for a small clinical fit-out.
Questions fréquentes
Why does equipment wait?
It needs delivery and medical-gas readiness.
What is commissioning?
It verifies the wing is ready for use.
Can equipment be ordered early?
Yes, after layout approval.