BESS

20 MW utility-scale BESS substation

This utility-scale BESS single line diagram represents a 20 MW storage plant built from two equal battery and PCS blocks. Each 10 MWh DC block connects to a 10 MW power conversion system. Their 690 V outputs meet on a collection bus and are transformed to 34.5 kV for the grid point of interconnection.

UPDATED 2026-09-23
TYPESld
USE-CASEBess Storage
EXAMPLE20 MW utility-scale BESS substation
Make this diagram your own.

Open it in the AI editor with a prompt pre-filled — keep what works, change what doesn't.

CASE ANALYSIS

Scenario

A grid-connected storage plant combines two PCS blocks before exporting or importing power through one generator step-up transformer.

Key decisions

  • Each 10 MWh battery block has its own 10 MW PCS.
  • The PCS outputs combine on a 690 V bus before voltage transformation.
  • The 25 MVA GSU provides capacity above the 20 MW nominal conversion rating.
  • An intertie breaker and 25/27/81 relay protect the 34.5 kV point of interconnection.

When to reuse this

This pattern suits a modular utility-scale BESS with a collector-system interconnection. The final project requires detailed relay coordination, grounding, and utility telemetry design.

FAQ

Frequently asked questions

Why are PCS blocks modular?01
Modular PCS blocks simplify procurement, maintenance, and staged expansion.
What is a GSU transformer?02
A generator step-up transformer raises low-voltage PCS output to the medium-voltage interconnection level.
What do 25/27/81 mean?03
They are ANSI device numbers for synchronism check, undervoltage, and frequency protection functions.