“Create a software release estimate timeline with three-point durations for specification, build, security review, test, fixing findings, and deployment.”
図の背後にある意思決定を読み解く。
Use optimistic, likely and pessimistic values.
Security review and testing both follow the build.
Deployment waits for review and test issues to be addressed.
Use when a release estimate needs to show uncertainty and dependency rather than a single fixed duration.
よくある質問
What is a three-point estimate?
It records optimistic, most likely and pessimistic duration values for an activity.
Why run testing and security review in parallel?
They are separate activities that can both begin after a completed build.
What should deployment depend on?
It should depend on the resolution of findings from the required review and test work.