ChatDiagram
Project management · Software development

Software release estimate timeline

A software release estimate timeline uses three-point estimates to show uncertainty in each major task. Instead of one duration, each activity has an optimistic, likely and pessimistic value. After the build, security review and testing can proceed in parallel, while deployment waits until findings are resolved. This gives a planning conversation more realism than a single date. Update the estimates as evidence improves and use the dependency view to identify the work that controls release timing.

유형 PERT / 간트표준 PMI PMBOK 7 + Moder 1983 (AON/PDM)엔진 schematex-pert업데이트됨 2026. 9. 24.
Software release estimate
Drawing preview
요청 내용

“Create a software release estimate timeline with three-point durations for specification, build, security review, test, fixing findings, and deployment.”

그렇다면Add a user acceptance test after testing.Change the build estimate to 6, 10, and 16 days.
이 도면에 담긴 내용

그 이면의 의사결정을 읽어 보세요.

01Estimate uncertainty

Use optimistic, likely and pessimistic values.

02Run reviews in parallel

Security review and testing both follow the build.

03Join findings

Deployment waits for review and test issues to be addressed.

Use when a release estimate needs to show uncertainty and dependency rather than a single fixed duration.

모든 PERT / 간트 템플릿 보기 →

자주 묻는 질문

자주 묻는 질문

What is a three-point estimate?

It records optimistic, most likely and pessimistic duration values for an activity.

Why run testing and security review in parallel?

They are separate activities that can both begin after a completed build.

What should deployment depend on?

It should depend on the resolution of findings from the required review and test work.