ChatDiagram
PERT Chart · Pert

Three-point (PERT) estimation with variance — PERT Chart

Durations written as optimistic/most-likely/pessimistic (O/M/P). The engine computes the beta-distribution expected duration te = (O+4M+P)/6 per activity, the per-task variance, and the project-level standard deviation along the critical path.

유형 PERT / 간트표준 PMI PMBOK 7 + Moder 1983 (AON/PDM)엔진 schematex-pert업데이트됨 2026. 5. 26.
Three-point (PERT) estimation with variance
Drawing preview

모든 PERT / 간트 템플릿 보기 →