Three-point (PERT) estimation with variance — PERT Chart

Durations written as optimistic/most-likely/pessimistic (O/M/P). The engine computes the beta-distribution expected duration te = (O+4M+P)/6 per activity, the per-task variance, and the project-level standard deviation along the critical path.

Type PERT / CPM network & Gantt chartStandard PMI PMBOK 7 + Moder 1983 (AON/PDM)Engine schematex-pertUpdated 5/26/2026
Three-point (PERT) estimation with variance
Drawing preview