“Create an activity-on-arrow diagram for a lab installation: confirm scope, approve utilities, deliver equipment, prepare benches, fit extraction, then commission the lab.”
看懂背後的決策。
Equipment preparation begins only after utilities are approved.
Delivery, benches and extraction run in parallel.
Commissioning requires every installation stream.
Use this network for equipment installation where several site preparations converge on a commissioning event.
常見問題
Why is utility approval early?
It confirms that the site can support the planned installation.
Can delivery overlap preparation?
Yes, both begin after utility approval.
What is commissioning?
It is the final activity that verifies the lab is ready to operate.