“Create an activity-on-arrow diagram for a lab installation: confirm scope, approve utilities, deliver equipment, prepare benches, fit extraction, then commission the lab.”
Read the decisions behind it.
Equipment preparation begins only after utilities are approved.
Delivery, benches and extraction run in parallel.
Commissioning requires every installation stream.
Use this network for equipment installation where several site preparations converge on a commissioning event.
Other examples in this family.
Common questions
Why is utility approval early?
It confirms that the site can support the planned installation.
Can delivery overlap preparation?
Yes, both begin after utility approval.
What is commissioning?
It is the final activity that verifies the lab is ready to operate.