Q3 product launch PERT/CPM network — PERT Chart

A seven-task product-launch schedule where the engine computes every Early/Late Start & Finish, total slack, and the critical path (A → C → D → E → G) automatically — the canonical activity-on-node network with the six-field box.

Typ PERT / GanttStandard PMI PMBOK 7 + Moder 1983 (AON/PDM)Engine schematex-pertAktualisiert 26.5.2026