A seven-task product-launch schedule where the engine computes every Early/Late Start & Finish, total slack, and the critical path (A → C → D → E → G) automatically — the canonical activity-on-node network with the six-field box.

類型 PERT/甘特圖標準 PMI PMBOK 7 + Moder 1983 (AON/PDM)引擎 schematex-pert更新時間 2026/5/26
Q3 product launch PERT/CPM network