ChatDiagram
project planning · facilities

Office move AON diagram

This activity-on-node diagram shows the dependency structure of a small office move. Approval releases furniture ordering and network planning. Furniture ordering leads to site preparation, while network planning leads to network installation. The team moves only after both readiness paths are complete. The diagram keeps facilities and IT work distinct while making the final handover dependency clear. It is useful for office managers, IT coordinators and contractors who need a shared plan before the move date is announced. Add tasks for access control, cleaning, equipment delivery or a phased move when those conditions apply.

Type PERT / GanttNorme PMI PMBOK 7 + Moder 1983 (AON/PDM)Moteur schematex-pertMis à jour 24/09/2026
Office move AON
Drawing preview
La demande

“Create an activity-on-node diagram for an office move: approve the move, order furniture, plan the network, prepare the site, install the network, then move the team.”

Essayez ensuiteAdd a two-day security setup before moving the team.Change furniture ordering to take seven days.
Ce que contient ce dessin

Comprenez les décisions qui le sous-tendent.

01Move approval

Furniture and network planning begin after approval.

02Separate readiness paths

Site preparation and network installation proceed independently.

03Move gate

Staff move only when the site and network are ready.

Use this AON network for relocations where facilities and IT must finish together.

Voir tous les modèles de PERT / Gantt →

FAQ

Questions fréquentes

Why is the move last?

It waits for the physical site and the network to be ready.

Can facilities and IT overlap?

Yes, their preparation paths start after move approval.

What can be added?

Add security, cleaning or equipment-delivery tasks with their predecessors.