“Create an activity-on-node diagram for an office move: approve the move, order furniture, plan the network, prepare the site, install the network, then move the team.”
פענחו את ההחלטות שמאחוריו.
Furniture and network planning begin after approval.
Site preparation and network installation proceed independently.
Staff move only when the site and network are ready.
Use this AON network for relocations where facilities and IT must finish together.
שאלות נפוצות
Why is the move last?
It waits for the physical site and the network to be ready.
Can facilities and IT overlap?
Yes, their preparation paths start after move approval.
What can be added?
Add security, cleaning or equipment-delivery tasks with their predecessors.