Office move AON diagram
This activity-on-node diagram shows the dependency structure of a small office move. Approval releases furniture ordering and network planning. Furniture ordering leads to site preparation, while network planning leads to network installation. The team moves only after both readiness paths are complete. The diagram keeps facilities and IT work distinct while making the final handover dependency clear. It is useful for office managers, IT coordinators and contractors who need a shared plan before the move date is announced. Add tasks for access control, cleaning, equipment delivery or a phased move when those conditions apply.
Open it in the AI editor with a prompt pre-filled — keep what works, change what doesn't.
Scenario
A facilities team prepares an office before staff move in.
Key decisions
- Move approval: Furniture and network planning begin after approval.
- Separate readiness paths: Site preparation and network installation proceed independently.
- Move gate: Staff move only when the site and network are ready.
When to reuse this
Use this AON network for relocations where facilities and IT must finish together.
Frequently asked questions
Why is the move last?
Can facilities and IT overlap?
What can be added?
More project planning examples
Try the diagram makers.
Tweak it with chat, export PNG/SVG, or fork it for your own use case.