ERP rollout critical path

This critical path diagram maps the decisions and dependencies in a compact ERP rollout. Scope confirmation releases configuration and data cleaning. Configuration supports both user training and migration testing, while data cleaning is also required before the migration test. Go-live waits for training and the tested migration path. The network helps a delivery lead distinguish activities that can overlap from the dependencies that cannot move. Adapt it for integration testing, cutover rehearsal, support readiness and approval gates in a real implementation.

סוג PERT / גאנטתקן PMI PMBOK 7 + Moder 1983 (AON/PDM)מנוע schematex-pertעודכן 24.9.2026
ERP rollout critical path
Drawing preview
הבקשה

“Create a critical path diagram for an ERP rollout: confirm scope, configure the ERP, clean data, train users, test migration, then go live.”

ואז נסוAdd a two-day security review before go-live.Change data cleaning to take eight days.
מה מופיע בתרשים הזה

פענחו את ההחלטות שמאחוריו.

01Scope gate

Configuration and data work start after scope.

02Readiness paths

Training and migration testing converge.

03Go-live gate

Both readiness paths must finish.

Use for a concise enterprise-system rollout.

עיון בכל תבניות ה־PERT / גאנט ←

שאלות נפוצות

שאלות נפוצות

Why test migration?

It verifies configuration and cleaned data before go-live.

Can training overlap data cleaning?

Yes, after configuration is complete.

What delays go-live?

Training or migration testing delays.