ERP rollout critical path

This critical path diagram maps the decisions and dependencies in a compact ERP rollout. Scope confirmation releases configuration and data cleaning. Configuration supports both user training and migration testing, while data cleaning is also required before the migration test. Go-live waits for training and the tested migration path. The network helps a delivery lead distinguish activities that can overlap from the dependencies that cannot move. Adapt it for integration testing, cutover rehearsal, support readiness and approval gates in a real implementation.

유형 PERT / 간트표준 PMI PMBOK 7 + Moder 1983 (AON/PDM)엔진 schematex-pert업데이트됨 2026. 9. 24.
ERP rollout critical path
Drawing preview
요청 내용

“Create a critical path diagram for an ERP rollout: confirm scope, configure the ERP, clean data, train users, test migration, then go live.”

그렇다면Add a two-day security review before go-live.Change data cleaning to take eight days.
이 도면에 담긴 내용

그 이면의 의사결정을 읽어 보세요.

01Scope gate

Configuration and data work start after scope.

02Readiness paths

Training and migration testing converge.

03Go-live gate

Both readiness paths must finish.

Use for a concise enterprise-system rollout.

모든 PERT / 간트 템플릿 보기 →

자주 묻는 질문

자주 묻는 질문

Why test migration?

It verifies configuration and cleaned data before go-live.

Can training overlap data cleaning?

Yes, after configuration is complete.

What delays go-live?

Training or migration testing delays.