ERP rollout critical path

This critical path diagram maps the decisions and dependencies in a compact ERP rollout. Scope confirmation releases configuration and data cleaning. Configuration supports both user training and migration testing, while data cleaning is also required before the migration test. Go-live waits for training and the tested migration path. The network helps a delivery lead distinguish activities that can overlap from the dependencies that cannot move. Adapt it for integration testing, cutover rehearsal, support readiness and approval gates in a real implementation.

類型 PERT/甘特圖標準 PMI PMBOK 7 + Moder 1983 (AON/PDM)引擎 schematex-pert更新時間 2026/9/24
ERP rollout critical path
Drawing preview
需求

“Create a critical path diagram for an ERP rollout: confirm scope, configure the ERP, clean data, train users, test migration, then go live.”

接著試試Add a two-day security review before go-live.Change data cleaning to take eight days.
這張圖裡有什麼

看懂背後的決策。

01Scope gate

Configuration and data work start after scope.

02Readiness paths

Training and migration testing converge.

03Go-live gate

Both readiness paths must finish.

Use for a concise enterprise-system rollout.

瀏覽所有 PERT/甘特圖 範本 →

常見問題

常見問題

Why test migration?

It verifies configuration and cleaned data before go-live.

Can training overlap data cleaning?

Yes, after configuration is complete.

What delays go-live?

Training or migration testing delays.