情境

Design a single-line diagram for a residential/commercial solar-plus-storage system under UK G99/G100 grid codes, featuring an SMA Sunny Tripower 15kW inverter, battery storage, and demand response capability.

這張圖裡有什麼

看懂背後的決策。

01

Used IEC graphical symbols for a 3-phase 400V system.

02

Placed a G100 export limitation relay between the meter and the main busbar to curtail export when required.

03

Added a controlled demand response load to absorb excess generation.

04

Modeled the PV and battery inverters as separate sources with individual circuit breakers.

When designing or documenting a grid-connected solar and battery system that must comply with UK Engineering Recommendation G99 (generation connection) and G100 (export limitation), especially with demand response integration.