Software Sprint AON Diagram

النوع PERT / Ganttالمعيار PMI PMBOK 7 + Moder 1983 (AON/PDM)المحرّك schematex-pertآخر تحديث 17‏/6‏/2026
Software Sprint AON Diagram
Drawing preview
الطلب

“Create an activity-on-node diagram for a software sprint: planning, backend development, frontend development, UI design, integration testing and sprint review.”

جرّب إذنAdd a one-day code review after backend development.Change frontend development to take three days.
ما الذي يتضمنه هذا الرسم

اقرأ القرارات الكامنة وراءه.

01

Used explicit task IDs and after-dependencies to define sequence

02

Assigned realistic durations to demonstrate a 9-day sprint

03

Chose AON layout for node-based activity representation

Use this structure to model any sequential/parallel project tasks where you need to compute critical path and identify schedule flexibility.