요청 내용
“Create an activity-on-node diagram for a software sprint: planning, backend development, frontend development, UI design, integration testing and sprint review.”
그렇다면Add a one-day code review after backend development.Change frontend development to take three days.
이 도면에 담긴 내용
그 이면의 의사결정을 읽어 보세요.
01
Used explicit task IDs and after-dependencies to define sequence
02
Assigned realistic durations to demonstrate a 9-day sprint
03
Chose AON layout for node-based activity representation
Use this structure to model any sequential/parallel project tasks where you need to compute critical path and identify schedule flexibility.