Software Sprint AON Diagram

유형 PERT / 간트표준 PMI PMBOK 7 + Moder 1983 (AON/PDM)엔진 schematex-pert업데이트됨 2026. 6. 17.
Software Sprint AON Diagram
Drawing preview
요청 내용

“Create an activity-on-node diagram for a software sprint: planning, backend development, frontend development, UI design, integration testing and sprint review.”

그렇다면Add a one-day code review after backend development.Change frontend development to take three days.
이 도면에 담긴 내용

그 이면의 의사결정을 읽어 보세요.

01

Used explicit task IDs and after-dependencies to define sequence

02

Assigned realistic durations to demonstrate a 9-day sprint

03

Chose AON layout for node-based activity representation

Use this structure to model any sequential/parallel project tasks where you need to compute critical path and identify schedule flexibility.