Software Sprint AON Diagram

Tipo PERT / GanttStandard PMI PMBOK 7 + Moder 1983 (AON/PDM)Motore schematex-pertAggiornato 17/06/2026
Software Sprint AON Diagram
Drawing preview
La richiesta

“Create an activity-on-node diagram for a software sprint: planning, backend development, frontend development, UI design, integration testing and sprint review.”

Prova alloraAdd a one-day code review after backend development.Change frontend development to take three days.
Cosa contiene questo disegno

Leggi le decisioni che ne stanno alla base.

01

Used explicit task IDs and after-dependencies to define sequence

02

Assigned realistic durations to demonstrate a 9-day sprint

03

Chose AON layout for node-based activity representation

Use this structure to model any sequential/parallel project tasks where you need to compute critical path and identify schedule flexibility.