Software Sprint AON Diagram

Type PERT / CPM network & Gantt chartStandard PMI PMBOK 7 + Moder 1983 (AON/PDM)Engine schematex-pertUpdated 6/17/2026
Software Sprint AON Diagram
Drawing preview
The request

“Create an activity-on-node diagram for a software sprint: planning, backend development, frontend development, UI design, integration testing and sprint review.”

Then tryAdd a one-day code review after backend development.Change frontend development to take three days.
What is in this drawing

Read the decisions behind it.

01

Used explicit task IDs and after-dependencies to define sequence

02

Assigned realistic durations to demonstrate a 9-day sprint

03

Chose AON layout for node-based activity representation

Use this structure to model any sequential/parallel project tasks where you need to compute critical path and identify schedule flexibility.