Manufacturing Process AON Diagram

種類 PERT / ガントチャート規格 PMI PMBOK 7 + Moder 1983 (AON/PDM)エンジン schematex-pert更新日 2026/6/17
Manufacturing Process AON Diagram
Drawing preview
依頼内容

“Create an activity-on-node diagram for manufacturing: procure raw materials, assemble components, inspect quality, package, prepare shipping documents, then ship.”

次はこちらAdd a two-hour machine setup before assembly.Change packaging to take eight hours.
この図に含まれるもの

図の背後にある意思決定を読み解く。

01

Assign realistic durations per activity, such as 8 hours for procurement and 12 hours for assembly.

02

Determine parallel tasks like documentation alongside packaging to reduce total process time.

03

Identify critical path activities (e.g., assembly, inspection, packaging) to prioritize resource allocation.

When mapping any linear or semi-parallel production or project process with clear dependencies and need for schedule analysis.