“Create an activity-on-node diagram for manufacturing: procure raw materials, assemble components, inspect quality, package, prepare shipping documents, then ship.”
接著試試Add a two-hour machine setup before assembly.Change packaging to take eight hours.
這張圖裡有什麼
看懂背後的決策。
01
Assign realistic durations per activity, such as 8 hours for procurement and 12 hours for assembly.
02
Determine parallel tasks like documentation alongside packaging to reduce total process time.
03
Identify critical path activities (e.g., assembly, inspection, packaging) to prioritize resource allocation.
When mapping any linear or semi-parallel production or project process with clear dependencies and need for schedule analysis.