“Create a critical path diagram for a house build: excavate, pour the foundation, frame the house, install the roof, rough in services, then complete final inspection.”
اقرأ القرارات الكامنة وراءه.
Framing starts after the foundation.
Roofing and services follow framing.
Inspection waits for both paths.
Use for a compact construction schedule.
أسئلة شائعة
What is critical?
The longest dependent sequence controls completion.
Can roofing overlap services?
Yes, both follow framing.
Why is inspection last?
It requires both work paths.