ChatDiagram
project planning · construction

House build critical path

This critical path diagram organizes a house build from excavation through inspection. Foundation and framing form the main structural sequence. After framing, roofing and service rough-in proceed in parallel and both must finish before final inspection. The network makes the handoff points clear and gives a manager a compact starting point for discussing durations and constraints. Add permitting, procurement, finishes and trade inspections when they affect the actual project. Review the critical sequence whenever a duration or predecessor relationship changes.

Type PERT / GanttNorme PMI PMBOK 7 + Moder 1983 (AON/PDM)Moteur schematex-pertMis à jour 24/09/2026
House build critical path
Drawing preview
La demande

“Create a critical path diagram for a house build: excavate, pour the foundation, frame the house, install the roof, rough in services, then complete final inspection.”

Essayez ensuiteAdd a two-day permit check before excavation.Change framing to take ten days.
Ce que contient ce dessin

Comprenez les décisions qui le sous-tendent.

01Foundation gate

Framing starts after the foundation.

02Parallel work

Roofing and services follow framing.

03Finish gate

Inspection waits for both paths.

Use for a compact construction schedule.

Voir tous les modèles de PERT / Gantt →

FAQ

Questions fréquentes

What is critical?

The longest dependent sequence controls completion.

Can roofing overlap services?

Yes, both follow framing.

Why is inspection last?

It requires both work paths.