House build critical path

This critical path diagram organizes a house build from excavation through inspection. Foundation and framing form the main structural sequence. After framing, roofing and service rough-in proceed in parallel and both must finish before final inspection. The network makes the handoff points clear and gives a manager a compact starting point for discussing durations and constraints. Add permitting, procurement, finishes and trade inspections when they affect the actual project. Review the critical sequence whenever a duration or predecessor relationship changes.

Tipo PERT / GanttNorma PMI PMBOK 7 + Moder 1983 (AON/PDM)Mecanismo schematex-pertAtualizado 24/09/2026
House build critical path
Drawing preview
A solicitação

“Create a critical path diagram for a house build: excavate, pour the foundation, frame the house, install the roof, rough in services, then complete final inspection.”

Depois, tenteAdd a two-day permit check before excavation.Change framing to take ten days.
O que há neste desenho

Entenda as decisões por trás dele.

01Foundation gate

Framing starts after the foundation.

02Parallel work

Roofing and services follow framing.

03Finish gate

Inspection waits for both paths.

Use for a compact construction schedule.

Ver todos os modelos de PERT / Gantt →

Perguntas frequentes

Dúvidas comuns

What is critical?

The longest dependent sequence controls completion.

Can roofing overlap services?

Yes, both follow framing.

Why is inspection last?

It requires both work paths.