“Create a critical path diagram for a house build: excavate, pour the foundation, frame the house, install the roof, rough in services, then complete final inspection.”
Leggi le decisioni che ne stanno alla base.
Framing starts after the foundation.
Roofing and services follow framing.
Inspection waits for both paths.
Use for a compact construction schedule.
Domande frequenti
What is critical?
The longest dependent sequence controls completion.
Can roofing overlap services?
Yes, both follow framing.
Why is inspection last?
It requires both work paths.